First steel components for Guinea project reach the designated port

The first steel components for Zhonghengfeng’s Guinea project have completed fabrication, inspection, packing and inland transport and arrived safely at the designated port. The milestone confirms that the initial delivery route from the Baotou manufacturing base to the port is operating as planned.

Production of later batches is continuing at the factory according to the project schedule.

Packed blue steel components prepared for the first Guinea project shipment
Fabricated components are protected, marked and secured in steel transport frames.

Fabrication and inspection completed before dispatch

The first batch passed through material processing, cutting, assembly, welding, surface treatment and corrosion-protection work at Zhonghengfeng’s Baotou base. Before release, the team completed dimensional checks, weld inspection and other quality-control steps required by the project.

Production and inspection records link each component to its identification mark and packing information. This traceability supports document review during dispatch and helps the receiving team confirm the cargo after arrival.

Identification marking on packaged steel components for the Guinea project
Component marks and package records support shipment traceability.

Export packaging designed for handling and transport

The blue-painted steel members were grouped by delivery package and protected at contact points before loading. Steel frames, straps and wrapping help control movement and protect finished surfaces during handling and transport.

Packaged steel components staged at Zhonghengfeng's Baotou factory for Guinea
Completed packages are staged by batch before vehicle loading.

Package dimensions and weights were reviewed against the transport plan before dispatch. Components from different building areas were kept identifiable so the cargo could be sorted efficiently at the next logistics stage.

First batch of Guinea project steel components loaded onto a flatbed truck
The first batch leaves the manufacturing base for the designated port.

First batch arrives safely at the port

After road transport from Baotou, the first batch reached the designated port and completed unloading. The delivery provides a tested workflow for vehicle scheduling, cargo reception, weighing and handling that can be reused for the project’s later batches.

Guinea project steel components being unloaded after arrival at the designated port
Port staff unload the first batch of fabricated steel components.

Later Guinea project batches remain in production

Zhonghengfeng’s Baotou base covers approximately 100,000 square metres and has a monthly steel structure capacity of more than 10,000 tonnes. Fabrication of the remaining Guinea project components is continuing in planned batches to support production flow and logistics coordination.

More information about the project’s packaging, coating and traceability system is available in our report on managing the steel structure export to Guinea. Buyers can also review Zhonghengfeng’s quality-control process or contact the project team about steel fabrication and export logistics.